Project Management Week 4 NPTEL Assignment Answers 2025

Need help with this week’s assignment? Get detailed and trusted solutions for Project Management Week 4 NPTEL Assignment Answers. Our expert-curated answers help you solve your assignments faster while deepening your conceptual clarity.

✅ Subject: Project Management
📅 Week: 4
🎯 Session: NPTEL 2025 July-October
🔗 Course Link: Click Here
🔍 Reliability: Verified and expert-reviewed answers
📌 Trusted By: 5000+ Students

For complete and in-depth solutions to all weekly assignments, check out 👉 NPTEL Project Management Week 4 NPTEL Assignment Answers

🚀 Stay ahead in your NPTEL journey with fresh, updated solutions every week!

NPTEL Project Management Week 4 Assignment Answers 2024

1. Breaking the project scope down to manageable units of work is termed as?

  • Event breakdown
  • Scope breakdown
  • Time breakdown
  • Work breakdown
Answer : See Answers

2. The Common characteristics of a project are

  • They are complex and unique
  • They are limited by budget, schedule, and resources
  • They have a clear goal or set of goals
  • All of the above
Answer :

3. A project manager is reviewing the work breakdown structure for her project. The WBS of the project represents

  • all the tangible items that must be delivered to the client.
  • all the work that must be completed for the project.
  • the work that must be performed by the project team.
  • all the activities of the project.
Answer :

4. A task was scheduled to use two persons, full time, and take two weeks to complete. Instead, the project manager was only able to assign one person to this task. At the end of two weeks, the person assigned to the task was 75% complete. What is the cost performance index?

  • 0.75
  • 1.5
  • 1.33
  • 0.5
Answer :

5. Schedules are used in many ways. In a project to build a bridge the project manager wants to use a tool that will show the scheduled activities in such a way that it is easy to see when each activity starts and finishes and which activities are taking place at the same time. Which tool should be used?

  • PERT chart
  • Gantt chart
  • Precedence diagram
  • GERT chart
Answer :

6. What is the underlying principle behind the Safety First Principle?

  • Decision maker is always risk averse.
  • Safety against risky investments is the prime objective
  • The decision maker is unable or unwilling to consider the utility theorem for making his/her decision process.
  • Bad outcomes are given more importance to ensure safety against risky investments.
Answer : See Answers

7. Chebyshev’s inequality states that the probability of a “Six Sigma” event is less than :

  • 10%
  • 20%
  • 30%
  • 3%
Answer :

8. The Precedence Diagramming Method (PDM) represents activities on arrows, while the Arrow Diagramming Method (ADM) uses nodes for activities.

  • True
  • False
Answer :

9. Chebyshev’s inequality indicates that the probability of a Six Sigma event is less than 3%.

  • True
  • False
Answer :

10. The Precedence Diagramming Method (PDM) represents activities on arrows, while the Arrow Diagramming Method (ADM) uses nodes for activities.

  • True
  • False
Answer : See Answers

NPTEL Project Management Week 4 Assignment Answers 2024

1. _____________is a critical process that organisations undertake to assess the viability, sustainability, and potential success of a proposed project before committing significant resources.

  • A. Project estimation
  • B. Project feasibility analysis
  • C. Project Monitoring
  • D. Launch meeting

Answer: B. Project feasibility analysis
Explanation: Project feasibility analysis evaluates whether a project is realistic and achievable based on factors like technical requirements, cost, and time. It’s done before investing resources to ensure the project has a chance of success.


2. ____________ is a plan for allocating resources. The allocation of resources indicates the degree to which different activities of an organisation are supported fully.

  • A. A budget
  • B. Direct cost
  • C. A management plan
  • D. An allocation effort

Answer: A. A budget
Explanation: A budget outlines how an organization’s resources will be distributed to various activities or departments. It reflects the priorities and support levels for each function.


3. The ____________ form of budgeting has the advantage of using individuals closer to the work to provide estimates of resource requirements.

  • A. top-down budgeting
  • B. work element costing
  • C. bottom-up budgeting
  • D. iterative budgeting

Answer: C. bottom-up budgeting
Explanation: Bottom-up budgeting involves those directly involved in the tasks to provide cost and resource estimates. This often results in more accurate planning.


4. Which of the following is not a type of quantitative risk analysis?

  • A. Failure Mode and Effects Analysis
  • B. decision tree analysis
  • C. Monte Carlo simulations
  • D. expert judgment

Answer: A. Failure Mode and Effects Analysis
Explanation: FMEA is generally a qualitative tool used to identify potential failure modes, their causes, and effects. Quantitative techniques use numerical data to evaluate risks.


5. In risk response planning, where the goal of the project manager is to increase the probability that the opportunity will occur, the project manager must ________

  • A. exploit
  • B. share
  • C. enhance
  • D. accept

Answer: C. enhance
Explanation: Enhancing is a risk response strategy aimed at increasing the likelihood of positive risks (opportunities). It involves actions to make the opportunity more likely to occur.


6. A(n) __________ is the conversion of the project work breakdown structure into an operating timetable.

  • A. chart
  • B. application
  • C. crash
  • D. schedule

Answer: D. schedule
Explanation: A schedule translates the Work Breakdown Structure (WBS) into a time-based plan, showing when each task or deliverable will be started and completed.


7. The activities that take place at the same time

  • A. Sequential activities
  • B. Parallel activities
  • C. Immediate predecessor
  • D. Successor

Answer: B. Parallel activities
Explanation: Parallel activities are those that can be executed simultaneously, reducing the overall project duration when managed correctly.


8. Which type of project has the critical path method (CPM) primarily been used for?

  • A. Construction
  • B. Manufacturing
  • C. Industrial
  • D. Research and development

Answer: A. Construction
Explanation: CPM is most widely used in the construction industry, where it’s vital to manage project timelines, resources, and dependencies efficiently.


9. The difference between the late start and early start for an activity is called its _________.

  • A. critical path
  • B. task
  • C. progress
  • D. slack

Answer: D. slack
Explanation: Slack (or float) is the amount of time that an activity can be delayed without delaying the project. It’s key in identifying schedule flexibility.


10. Which is the below-mentioned rule? “The earliest start time for an activity is equal to the largest (i.e., latest) of the earliest finish times for all its immediate predecessors.”

  • A. Backward pass
  • B. Variance
  • C. Forward pass
  • D. Slack

Answer: C. Forward pass
Explanation: The forward pass technique calculates the earliest start and finish times by moving forward through the project network diagram from start to end.