Project Management Week 5 NPTEL Assignment Answers 2025

Need help with this week’s assignment? Get detailed and trusted solutions for Project Management Week 5 NPTEL Assignment Answers. Our expert-curated answers help you solve your assignments faster while deepening your conceptual clarity.

✅ Subject: Project Management
📅 Week: 5
🎯 Session: NPTEL 2025 July-October
🔗 Course Link: Click Here
🔍 Reliability: Verified and expert-reviewed answers
📌 Trusted By: 5000+ Students

For complete and in-depth solutions to all weekly assignments, check out 👉 NPTEL Project Management Week 5 NPTEL Assignment Answers

🚀 Stay ahead in your NPTEL journey with fresh, updated solutions every week!

NPTEL Project Management Week 5 Assignment Answers 2025

1. Which is/are features of PERT/CPM?

  • An estimate of how long a project will take.
  • A graphical display of project activities.
  • An indication of critical activities.
  • All the above
Answer : See Answers

2. In PERT, slack time equals

  • EST + t
  • LST – EST
  • Zero
  • EFT – EST
Answer :

3. Which of the following is one of the assumptions of PERT?

  • Total project completion time follows a normal probability distribution.
  • Activity times are dependent and correlated.
  • Project completion time follows a skewed chi-square distribution.
  • Activity times are known with certainty.
Answer :

For the Project network shown, answer the Questions 4 and 5 based on the data
provided.

4. What is the critical path?

  • A-B-E-H-K
  • A-B-E-G-J
  • C-D-E-G-I-K
  • C-D-E-G-J
Answer :

5. What is the probability of meeting a desired 26 weeks completion time?

  • 0.2159
  • 0.2060
  • 0.2476
  • 0.1867
Answer :

6. An important assumption in PERT calculations is:

  • Activity times are normally distributed.
  • Activity times are independent.
  • A and B
  • A and C
Answer : See Answers

7. If t a , t m and t b are the optimistic time, most likely time and pessimistic time respectively in PERT network then the expected value formulae is

  • (t a + 3tm + tb )/6
  • (ta + 4t m + t b )/6
  • (ta – 4tm + tb )/6
  • (ta – 3tm + t b )/6
Answer :

8. For Question # 8 to Question # 10 one should use data given which is as follows:
The tasks, their respective precedence and their respective times for a job which has these activities, are given as follows

The time to complete the job is

  • 21
  • 24
  • 26
  • 27
Answer :

9. The ES and EF for activity C is

  • ES = 0 and EF = 2
  • ES = 10 and EF = 13
  • ES = 5 and EF = 8
  • ES = 7 and EF = 10
Answer :

10. Float is available for activity/activities

  • Activities A and B
  • Activity A
  • Activity B
  • Activities C and D
Answer : See Answers

NPTEL Project Management Week 5 Assignment Answers 2024

1. Project task E has the following estimates: (1) optimistic time – 10 days, (2) Pessimistic time – 20 days, and (3) Most likely time – 12 Days. The standard deviation for time using the beta statistical distribution is ______________ days.

  • 1.5
  • 1.67
  • 2
  • 2.33

Answer: 1.67

Explanation:
Standard deviation (σ) = (Pessimistic – Optimistic) / 6 = (20 – 10)/6 = 1.67


2. Variance of an activity, σ² =

  • ((a+b)/6)²
  • (b-a)² / 6
  • ((b-a)/6)²
  • (a-b)²

Answer: ((b-a)/6)²

Explanation:
Variance = [ (Pessimistic – Optimistic) / 6 ]² = ((b-a)/6)²


3. Which of the following is not an advantage of a Gantt chart?

  • It can be easily understood
  • Gantt charts are more effective for huge projects than ordinary projects
  • It provides a good picture of the state of the project
  • It is relatively easy to maintain

Answer: Gantt charts are more effective for huge projects than ordinary projects

Explanation:
Gantt charts become cluttered and hard to interpret in large and complex projects.


4. One method of managing uncertainty is to perform ___________ on the data involved in our managerial decisions

  • Simulation
  • Probability analysis
  • Critical path analysis
  • Risk analysis

Answer: Probability analysis

Explanation:
Probability analysis helps evaluate different outcomes and uncertainties using statistical models.


5. Which of the following is not a reason for using Scrum for scheduling?

  • Flexibility and Adaptability
  • Customer Feedback
  • Transparency
  • Resistance

Answer: Resistance

Explanation:
Scrum is known for promoting adaptability, transparency, and feedback. Resistance is not a benefit, it’s a challenge.


6. The formula for computing the cost/time slope for each activity that can be crashed is ____________.

  • (crash cost + normal cost) / (crash time + normal time)
  • (crash cost – normal cost) / (crash time – normal time)
  • (normal cost + crash cost) / (normal time + crash time)
  • (normal cost – crash cost) / (normal time – crash time)

Answer: (crash cost – normal cost) / (crash time – normal time)

Explanation:
Slope = (Crash Cost – Normal Cost) / (Normal Time – Crash Time)


7. If the crash cost is $2,500, the normal cost is $1,500, the crash time is 4, and the normal time is 6, what is the slope?

  • -1,500
  • -1,000
  • +750
  • -500

Answer: -500

Explanation:
Slope = (2500 – 1500) / (6 – 4) = 1000 / 2 = +500, but time reduces, so cost per day saved is -500.


8. ______________ describes the amounts of individual resources an existing schedule requires during specific time periods.

  • Resource loading
  • Resource leveling
  • Scope loading
  • Resource succeeding

Answer: Resource loading

Explanation:
Resource loading shows how much of a resource is needed during a specific period in the project schedule.


9. _____________ itself is always a critical resource in project management, one that is unique because it can neither be inventoried nor renewed.

  • Crashed resources
  • Labor
  • Manpower
  • Time

Answer: Time

Explanation:
Time is the only non-renewable resource in project management; once lost, it cannot be recovered.


10. A project task is said to be __ if it requires a fixed amount of time and known quantities of resources.

  • scope constrained
  • time constrained
  • resource constrained
  • system constrained

Answer: time constrained

Explanation:
Time-constrained tasks must be completed within a fixed schedule regardless of resource availability.